Q:   What is the timeframe for major milestones?

A: Permitting milestones are subject to agency discretion of permitting activities. Current target milestones include:


April 2005 - Submittal of Federal Section 10 permit application


• 2006 - Submittal of Article VII application

• Late 2007 - Permit approvals

• Late 2007 - Equipment procurement, transportation and staging

• Early 2008 - Transmission line burial construction

• Spring 2008 - Wind Park construction begins

• Fall 2008 - Wind Park operation